PMP Quiz 12 October 2018

You're involving the business analyst, the designers and engineers, the quality and testing experts, and the representatives from the business in planning, and are reviewing the key information available to help make the best decisions for the project. Which of the following information about the project would never be available during project planning?
  • Budget at completion
  • Benefit-cost ratio
  • Cost performance index
  • Internal rate of return