PMP Quiz 15 February 2019

After much negotiation with stakeholders, you have drafted a project scope statement. Your subject matter experts have identified risks as they outlined deliverables and the needed work to complete them. Your next major deliverable is a project schedule. Because of the strict time constraints imposed on the project by the sponsor, you want to consider all relevant information when creating the schedule. All of the following are inputs to the Develop Schedule process except:
  • Organizational process assets, activity attributes, resource calendars
  • Schedule baseline, scope statement, risk register
  • Network diagrams, organizational process assets, agreements
  • Resource requirements, schedule management plan, lessons learned