PMP Quiz 18 February 2019

During the identification of risks on your project, you have determined there is a very high probability of conflict among the team during project executing over one aspect of the final design of the project. Which of the following is an example of mitigating the impact of the risk to the project?
  • Eliminate that part of the project.
  • Outsource that part of the project to another company.
  • Provide the team with training on conflict resolution techniques.
  • Obtain an insurance policy for the anticipated cost of the impact.