PMP Quiz 18 January 2019

While completing a project, a worker strike in the seller's city has resulted in the required deliverable being late. What is generally the best thing for the project manager to do?
  • Extend the contract for the length of the delay.
  • Tell the seller to stop work on the project until the strike is settled.
  • Remind the seller they are under contract to complete the project by the due date or they will be in default on the project.
  • Investigate ways to shorten other parts of the project in order to meet the seller's project completion date.