PMP Quiz 19 February 2019

The work specified in the procurement statement of work is completed on a project. However, the customer is not happy because she wants additional work to be completed. In light of this, what should be done?
  • Tell the customer it is too late to make a change.
  • Change to a cost-reimbursable contract.
  • Begin procurement closure and create a new contract for the additional work.
  • Add to the procurement statement of work, and proceed with additional work after obtaining management's agreement.