Which of the following is correct?
  • Define Scope and make-or-buy decisions are parts of the Plan Procurement Management process.
  • Cost estimates are best created by the person doing the work and the detailed project cost budget is created by management.
  • Inspecting is part of project control, and order of magnitude estimates are in a range of +10 to -25 percent.