PMP Quiz 26 September 2018

Instead of celebrating the end of the project, the stakeholders are breathing a sigh of relief. None of them were confident the project would meet the end date. Which of the following is probably not one of the reasons this project had difficulty?
  • Lack of a payback period
  • Lack of a communications management plan
  • Lack of a staffing management plan
  • Lack of milestones