PMP Quiz 27 September 2018

The project manager has noticed there have been a lot of changes on the project. This was not considered to be a problem until one day he discovers he cannot determine how many scope changes are currently being reviewed. This problem indicates an error in which of the following?
  • Lack of a change control board and constrained optimization
  • Change control system and project scope management plan
  • A poor change configuration system and benefit analysis
  • Plan purchases and acquisitions and requirements gathering